Current Projects

2021 PAVING PROGRAM 

The City of Norwich in conjunction with hired contractor, Charles Pasteryak Jr. Inc. have completed the following roads in 2021:

Curtis Street, Wilderness Road.

Philanne Drive, Aspen Court, Blueberry Hill Road, Mountainview Drive, Bayberry Hill Road, Lornadale Drive, Dalewood Drive, Knollcrest Road, Fernwood Street, Cottonwood Road, Barnsider Lane, Watson Drive

Otis Street, Perkins Ave, Francis Place.

Patrick Place, Lauren Lane, Woodlawn Terrace, Teddy Lane, Country Drive, Stone Cliff Lane, Old Salem Road, Carey Lane.

High Street, North High Street, Coit Street, Ann Street, Fairmount Street, Pearl Street.

 

2022 PAVING PROGRAM 

The following roads are tentatively planned to be re-paved in 2022:

Conn. Ave. Ext., Browning Rd., City Landing, Ferry St., Caribou Dr., Nemczuk Dr., Lincoln Ave., Norton Ct., Taylor Drive, and Williams St.

Thamesville Area: Westledge Dr., Clifton Pl., Elizabeth St. Ext., Oakwood Knoll, Pembroke Ave., Stanley Pl., and Westbrook Park

West Side Area: Johnson Pl., Maple St., and Wiley St.

Asylum Street Area: Carlson St., Fairview Ave., Monroe St., Overlook Rd., Sullivan Dr., and Western Ave.

Taftville Area: Evergreen St., portion of Lawler Lane, Melody Lane, and Sunrise St.

  

2021 Chip Sealing Program 

 

Nearly six and one half miles of roads were chip sealed in July, including; John Edwards Dr., Mohegan Park Road No. 2 (Hunters Rd. to the Beach parking lot), Montville Rd., Old Salem Rd. No. 1, Ox Hill Rd. (from Mahan Dr. to Wilderness Rd.), Rogers Rd. (Transfer Station to Wawecus Hill Rd.), and Wawecus Hill Rd.  

 

 

Replacement of the Sherman Street Bridges

The Final Design is nearly complete, with an anticipated Advertising for Bids in December, 2021.  Construction is expected to start in April of 2022. The construction phase will last two years, with closure of the bridges anticipated during the summer construction months.  

 

 

 Dunham Street Reconstruction

The project has been awarded to American Industries of Jewett City. There was a delay in the start because of the order time for granite curbing.  Some initial work such as tree removal has begun, but the majority of the work will be done in the spring of 2022.  This project entails a total reconstruction of Dunham St., complete with sidewalks on the entire length.

 

 Franklin Square Roundabout

The Nunes Companies Inc. completed this work in September, just in time for National Roundabout Week.

 

 Boswell Avenue Sidewalks

This sidewalk project was funded through a Community Development Block Grant in the amount of $200,000.  New sidewalk was installed by Evergreen Landscaping and Construction from Oak Street to Roath Street.  This project also included the reconstruction of 11 sets of concrete stairs and railings within the project limits. Work was completed in June.

 

 Uncas Leap Heritage Park

The abatement, selective demolition and stabilization of the granite mill building was completed in October.  The next phase of the project, which will utilize American Recovery Plan funds, is just starting.  The City is in the process of hiring a consultant to design the planned improvements to the Park, which will include a restroom facility, pathways, limited parking, overlooks, a story circle and site amenities such as benches, fencing improvements, and lighting.

 

New London Turnpike Rehabilitation

The City of Norwich, and the Town of Montville are joining forces to undertake a LOTCIP funded project which will reconstruct New London Turnpike from West Main Street to Route 32 in Montville.  Work will include new sidewalks and the rehabilitation of the bridge over Trading Cove Brook.  Currently we are in the process of selecting a design firm.

 

Revised November 24-2021